Project Updates 2018-2019

anticipated project schedule

Project Location Dates
CIPP Lining Project 6: 1300 N (West Point) October 2018 to
January 2019
1300N to 1081 N Just west of
4150 W (West Point)
January 2019 to March 2019
(Weather Permitting)
Highway 110/4500 West
(West Point)
January 2019 to March 2019
(Weather Permitting)
CIPP Lining Project 7: 4500 West, 2300 North, Kays Creek
Drive, and 6000 South
February 2019 to December 2019

Project Map

google 2018-2019 Project Work (Google Map)