Project Updates 2022

Anticipated Project Schedule

Project Location Dates
CIPP Lining Project 9: 4000 West (2200 S to 1700 S)
Syracuse City
Start December 2021
Completion July 2022
4500 West (1700 S to 1200 S)
Syracuse City
Start December 2021
Completion July 2022
CIPP Lining Project 10: 4000 West (1700 S to 700 S)
Syracuse City
TBD - 2022
3675 W / 5350 S / 5400 S / 5450 S
Roy City
TBD - 2022
3500 W / 3450 W / 5300 S
Roy City
TBD - 2022
3500 W / 3550 W / 5175 S
Roy City
TBD - 2022