Sewer Main Replacement - 2018-2019 Projects

Project Information and Updates

Project Location Dates
Master Plan Project 2A & 2B
(Line Repair)
Main Street (Layton) Start April 2019
Completion May 2019
Beecher Adams Line
Upsize - CIPP 7
Emerald Drive to private road
off Church Street
Start Spring 2019
Completion Fall 2019